46. Is it possible to change a Product Description once it has been approved?
  1. Yes, but only if the Project Manager deems it necessary.
  2. Yes, but only if the Project Board approves the change.
  3. Yes, but only via change control.
  4. No.
47. To which section of the Quality Management Strategy does the assignment of the Project Manager role belong?
  1. Roles and responsibilities
  2. Quality planning
  3. Quality assurance
  4. This is not part of the Quality Management Strategy.
48. As part of which process are decisions made regarding stage tolerance exceptions?
  1. Directing a Project
  2. Managing Stage Boundaries
  3. Controlling a Stage
  4. Managing Product Delivery
49. Which of the following statements is true?
  1. Management stages and technical stages must always be aligned.
  2. Technical stages may not overlap.
  3. Management stages may overlap.
  4. Technical stages may span a management stage boundary.
50. The Project Brief is assembled in which process?
  1. Starting up a Project
  2. Initiating a Project
  3. Directing a Project
  4. Controlling a Stage