Is it possible to change a Product Description once it has been approved?
  1. Yes, but only if the Project Manager deems it necessary.
  2. Yes, but only if the Project Board approves the change.
  3. Yes, but only via change control.
  4. No.
Explanation
Answer: C - Yes, but only via change control.

Key takeaway: The Product Description is a product, as with all documents in PRINCE2. Once a product has been approved, the only way to change it is through change control. This allows changes to be tracked back in the event there are any issues.