41. Which process can be carried out without using PRINCE2?
  1. Directing a Project.
  2. Starting up a Project.
  3. Managing Product Delivery.
  4. Closing a Project.
42. Which of the following is part of the PRINCE2 product based planning approach?
  1. Ensure each product has a Configuration Item record.
  2. Create the products.
  3. Test the products.
  4. Create the Product Breakdown Structure.
43. During which process is a Checkpoint Report produced?
  1. Managing Product Delivery
  2. Controlling a Stage
  3. Managing a Stage Boundary
  4. Directing a Project
44. Which PRINCE2 theme is one of the few to provide techniques?
  1. Planning
  2. Risk
  3. Organisation
  4. Progress
45.

Which of the following are valid responses to a Request for Change?

  1. Approve the change
  2. Defer decision
  3. Increase the tolerances
  4. Ask for an exception plan
  1. 1, 2
  2. 1, 2, 4
  3. 2, 3, 4
  4. 1, 2, 3, 4