The Project Brief is assembled in which process?
  1. Starting up a Project
  2. Initiating a Project
  3. Directing a Project
  4. Controlling a Stage
Explanation
Answer: A - Starting up a Project.

Key takeaway: The Project Brief describes the purpose of the project along with the cost, performance, time requirements, and constraints for starting the project. Since the Starting up a Project process is a pre-project activity, it is important that all this information is documented then, before the project is started in the Initiating a Project phase. The Project Brief is then used to create the Project Initiation Document.