Projects in Controlled Environments Foundation Practice Test - Question List

Select how would you like to study

51.

Which of the following roles must be mutually exclusive according to PRINCE2?

  1. Executive
  2. Project Manager
  3. Project Assurance
  4. Project Support
  1. 1, 2
  2. 2, 3
  3. 2, 4
  4. 3, 4
52. Which role is responsible for committing supplier resources to the Stage Plans?
  1. Executive
  2. Senior Supplier
  3. Project Manager
  4. Corporate or Programme Management
53.

What are the two types of progress controls provided by PRINCE2?

  1. Stage-driven
  2. Tolerance-driven
  3. Time-driven
  4. Event-driven
  1. 1, 2
  2. 1, 4
  3. 2, 3
  4. 3, 4
54.

Identifying a plan's critical path allows the Project Manager to monitor the activities that:

  1. Must be completed on time if the whole plan is to be finished on schedule
  2. Can be omitted if time tolerances are exceeded
  3. Are not allowed any time tolerance
  4. Can be delayed for a while if resources become tight
  1. 1, 2
  2. 2, 3
  3. 1, 4
  4. 3, 4
55. Which role is responsible for defining the role descriptions within the project?
  1. Corporate or Programme Management
  2. Executive
  3. Project Manager
  4. Project Support

Select how would you like to study