56. At what point is a Stage Plan updated with actuals?
  1. During the Managing a Stage Boundary process.
  2. As soon as actuals are received from a Work Package.
  3. Once a Work Package has been delivered.
  4. Once a Work Package has been approved.
57. There are at least how many valid business cases within the commercial context of any project?
  1. 0
  2. 1
  3. 2
  4. 3
58.

Which of the true is following about projects?

  1. They are driven by deliverables
  2. They have finite timescales
  3. They involve changes to the business capability
  4. They have benefits that are usually realized after project closure
  1. 1, 2
  2. 1, 2, 3
  3. 2, 3, 4
  4. 1, 2, 4
59. Product Descriptions are contained within which other product?
  1. Project Brief
  2. Project Initiation Documentation
  3. Stage Plan
  4. Benefits Review Plan
60.

The Product Description includes:

  1. Composition
  2. Format and Presentation
  3. Quality Responsibilities
  4. Item Attributes
  1. 1, 2, 3
  2. 2, 3, 4
  3. 1, 2, 4
  4. 1, 2, 3, 4