As part of which process are decisions made regarding stage tolerance exceptions?
  1. Directing a Project
  2. Managing Stage Boundaries
  3. Controlling a Stage
  4. Managing Product Delivery
Explanation
Answer: A - Directing a Project. The Project Board will make the decision.

Key takeaway: Decisions on tolerance exceptions are always made at the level that set the tolerances. For project tolerances, that would mean Corporate or Programme Management. For stage tolerances, it is the Project Board, and for Work Package tolerances, it is the Project Manager.
Was this helpful? Upvote!
Login to contribute your own answer or details

Top questions

Related questions

Most popular on PracticeQuiz