Projects in Controlled Environments Foundation Practice Test - Question List

Select how would you like to study

36.

What does it mean to tailor PRINCE2 to the project environment?

  1. Some elements of PRINCE2 should be omitted
  2. The principles should be adapted depending on the environment
  3. The methods should be adapted to suit the circumstances
  4. Blind obedience to project processes should be avoided
  1. 1 and 2
  2. 2 and 3
  3. 1 and 4
  4. 3 and 4
37. Who is responsible for communicating with stakeholders?
  1. Executive
  2. Senior User
  3. Project Manager
  4. Project Board
38.

At what point is the Stage Plan produced?

  1. During the Stage Boundary
  2. Starting up a Project
  3. Near the end of the previous stage
  4. Managing Product Delivery
39.

What should a Project Manager do when a stage tolerance is forecast to be exceeded?

  1. Create an Exception Report
  2. Recommend closing the project
  3. Add an entry to the Daily Log
  4. Update the Stage Plan
40.

What is the PRINCE2 term for a deliverable?

  1. Item
  2. Process
  3. Product
  4. Work Package