Which of the following are valid threat responses?

  1. Transfer
  2. Reject
  3. Share
  4. Fallback
  1. 1, 2
  2. 1, 3
  3. 1, 2, 3
  4. 1, 3, 4
7. Which of the following is NOT a PRINCE2 theme?
  1. Continued business justification
  2. Progress
  3. Organization
  4. Plans
8. Which role maintains the Quality Register?
  1. Project Support
  2. Project Manager
  3. Project Assurance
  4. Senior Supplier
9. Who is responsible for determining the Change Authority and change budget?
  1. Corporate or Programme Management
  2. Project Manager
  3. Project Board
  4. Executive
10.

Which document is used to record issues and risks in the Starting up a Project process if the appropriate registers have not yet been created?

  1. Lessons Log
  2. Daily Log
  3. Outline Business Case
  4. Project Brief