Projects in Controlled Environments Foundation Practice Test - Question List

Select how would you like to study

91.

Which of the following are optional when calculating the budget?

  1. Costs of Project Management activities
  2. Risk Budget
  3. Change Budget
  4. Cost Tolerances
  1. 1, 2
  2. 1, 4
  3. 2, 3
  4. 3, 4
92. During a Quality Review it is the responsibility of which role to request approval for the product?
  1. Presenter
  2. Chair
  3. Reviewer
  4. Administrator
93. Which of the following is NOT true for a PRINCE2 Plan?
  1. It describes how a specific target is to be achieved.
  2. It includes timescales and benefits for the defined targets.
  3. It contains sufficient information to confirm the targets are achievable.
  4. It includes named resources responsible for achieving the target.
94. Which process triggers the request to deliver a project?
  1. Starting up a Project
  2. Directing a Project
  3. Initiating a Project
  4. Managing Product Delivery
95.

A Change Authority is responsible for:

  1. Reviewing and approving/rejecting all requests for change/off-specifications within delegated limits set by the Project Board
  2. Reviewing and approving/rejecting all requests for change/off-specifications
  3. Monitoring the change budget
  4. Maintaining the Product Status Account