Projects in Controlled Environments Foundation Practice Test - Question List

Select how would you like to study

61. It is the responsibility of which role to review risk management practices and ensure that they are performed in line with the project's Risk Management Strategy?
  1. Project Assurance
  2. Project Manager
  3. Project Support
  4. Executive
62. A Risk Cause is which of the following?
  1. A threat
  2. Description of the source of the risk
  3. An objective
  4. A risk budget
63. Which role confirms acceptance of the Project Product?
  1. Project Assurance
  2. Corporate or Programme Management
  3. Project Manager
  4. Executive
64. Follow on action recommendations are made in which process?
  1. Starting up a Project
  2. Directing a Project
  3. Closing a Project
  4. Managing a Stage Boundary
65. Which of the following is NOT included in a plan?
  1. Dependencies
  2. Budgets
  3. Schedule
  4. Lessons learned