31.

Which of the following are fields in the Quality Register?

  1. Product identifier(s)
  2. Roles and responsibilities
  3. Reporting
  4. Quality records
  1. 1 and 4
  2. 1, 3, and 4
  3. 1, 2, and 4
  4. 1, 2, 3, and 4
32.

In which of the following reports are risks communicated?

  1. Checkpoint Reports
  2. Highlight Reports
  3. Lessons Reports
  4. End Project Reports
  1. 1, 2
  2. 1, 3
  3. 1, 2, 3
  4. 1, 2, 3, 4
33.

Which of the following activities is one of the responsibilities of a Team Manager?

  1. Liaise with any Project Assurance and Project Support roles
  2. Maintain the Issues Register
  3. Authorize Work Packages
  4. Assist the Project Manager in developing the Business Case
34.

When a work package is returned, which of the following actions does PRINCE2 recommend?

  1. Notify the Project Board
  2. Update the Team Plan
  3. Review the Approval Records
  4. Update the Stage Plan
  1. 1 and 2
  2. 2 and 3
  3. 1, 2, and 3
  4. 1, 3, and 4
35.

Which role has the responsibility of setting project tolerances?

  1. Corporate or Programme Management
  2. Executive
  3. Project Manager
  4. Project Board