Which of the following is part of the PRINCE2 product based planning approach?
  1. Ensure each product has a Configuration Item record.
  2. Create the products.
  3. Test the products.
  4. Create the Product Breakdown Structure.
Explanation
Answer: D - Create the Product Breakdown Structure.

Key takeaway: The product based planning approach consists of writing the Project Product Description for the Project Plan, followed by the creation of the breakdown structure, the individual product descriptions, and the product flow diagram.
Was this helpful? Upvote!
Login to contribute your own answer or details

Top questions

Related questions

Most popular on PracticeQuiz