Which process can be carried out without using PRINCE2?
  1. Directing a Project.
  2. Starting up a Project.
  3. Managing Product Delivery.
  4. Closing a Project.
Explanation
Answer: C - Managing Product Delivery. This sits outside the PRINCE2 framework.

Managing Product Delivery allows a PRINCE2 project to assign Work Packages to suppliers that may use different methodologies. In this way, the supplier can manage their own project in any way they choose, as long as they adhere to what is agreed in the Work Package (e.g. for reporting purposes).
Was this helpful? Upvote!
Login to contribute your own answer or details

Top questions

Related questions

Most popular on PracticeQuiz