During which process is a Checkpoint Report produced?
  1. Managing Product Delivery
  2. Controlling a Stage
  3. Managing a Stage Boundary
  4. Directing a Project
Explanation
Answer: A - Managing Product Delivery. The Checkpoint Report is made at a pre-determined frequency.

Key takeaway: The Work Package includes details of when Checkpoint Reports should be produced by the Team Manager for the Project Manager. These reports allow the Project Manager to monitor the status of the Work Package and ensure that it is on schedule.