Answer: B - Daily Log. Any issues or risks can be transferred to the Risk Register or Issue Register when they are created during the Initiating a Project process.
Key takeaway: During the Starting up a Project process there has been no stage boundary at which to review the business case and validity of the project, meaning the project does not yet have formal approval from the Project Board. This will occur (if everything is acceptable) following the request to initiate the project at the end of the stage.