Which role maintains the Quality Register?
  1. Project Support
  2. Project Manager
  3. Project Assurance
  4. Senior Supplier
Explanation
Answer: A - Project Support. This role is responsible for administrative aspects of the project.

Key takeaway: Although the Project Support role may be filled by the same person as the Project Manager role, the roles are still distinct within PRINCE2. Project Support is responsible for day-to-day administrative support of the project, including tasks such as configuration management and maintaining the Quality Register.
Was this helpful? Upvote!