Who is responsible for determining the Change Authority and change budget?
  1. Corporate or Programme Management
  2. Project Manager
  3. Project Board
  4. Executive
Explanation
Answer: D - Executive. It is the executive's decision alone as to who has responsibility for requests for change or off-specification items and the associated budget.

Key takeaway: The Executive represents the business interests on the project, which includes the funding for the project. Because of this, it is their sole responsibility to determine budgets and responsibilities for changes/off-specifications which might affect the overall cost.