Who can order the closure of a project?
  1. Project Manager
  2. Project Board
  3. Project Assurance
  4. Project Support
Explanation
Answer: B - Project Board. Any closure authorisation must come from the Project Board, even for the planned closure.

Key takeaway: The Project Manager can make a recommendation for the project to be closed either when the project comes to a natural end, or at any time during the project (such a recommendation would likely be included in an Exception Report). The ultimate decision lies with the Project Board in all cases.