Which of the following are valid responses to a Request for Change?

  1. Approve the change
  2. Defer decision
  3. Increase the tolerances
  4. Ask for an exception plan
  1. 1, 2
  2. 1, 2, 4
  3. 2, 3, 4
  4. 1, 2, 3, 4
Explanation

Answer: B - Increasing the tolerances is not an option.

Key takeaway: The Project Board can approve or reject the request, defer the decision, or ask for more information. They can also request an Exception Plan from the Project Manager. They cannot increase the tolerances to take the request into account and tolerances should never be used to fund Requests for Change.