Which process allows non-PRINCE2 practices to be integrated into a PRINCE2 project environment when creating products?
  1. Managing Product Delivery.
  2. Controlling a Stage.
  3. Directing a Project.
  4. Managing a Stage Boundary.
Explanation
Answer: A - Managing Product Delivery. This process allows a Team Manager to use their own procedures to manage the delivery of a work package.

Key takeaway: The interface between a Team Manager and a Project Manager is agreed when the Work Package is accepted. The Team Manager (who may be from another company) may then use whatever standards and processes they deem necessary to manage the work.