16. Which role(s) has/have ultimate authority on the Project Board?
  1. Senior Supplier
  2. Senior User
  3. Executive
  4. Joint authority
17.

Which roles must be independent of each other?

  1. Team Manager
  2. Project Support
  3. Project Manager
  4. Project Assurance
  1. 1, 3
  2. 2, 3
  3. 2, 4
  4. 3, 4
18. Which process provides information to the Project Board to allow them to assess the continuing viability of the project?
  1. Controlling a Stage.
  2. Directing a Project.
  3. Managing a Stage Boundary.
  4. Managing Product Delivery.
19. Which of the following roles can appoint the Project Manager?
  1. Executive
  2. Senior User
  3. Senior Supplier
  4. Project Assurance
20. Which of the following supports the PRINCE2 principle of Management by Exception?
  1. Delegation of authority.
  2. Creating the Product Flow Diagram.
  3. Maintaining the Business Case.
  4. Creating a Request for Change.