Which of the following is NOT a PRINCE2 theme?
  1. Continued business justification
  2. Progress
  3. Organization
  4. Plans
Explanation
Answer: A - Continued Business Justification. This is one of the 7 principles of PRINCE2.

Key takeaway: The 7 themes of PRINCE2 are areas within the project that must be considered throughout the lifespan of the project. The themes must all be applied to each PRINCE2 project in a suitable tailored manner.