Which of the following roles must be mutually exclusive according to PRINCE2?

  1. Executive
  2. Project Manager
  3. Project Assurance
  4. Project Support
  1. 1, 2
  2. 2, 3
  3. 2, 4
  4. 3, 4
Explanation

Answer: B - Project Manager and Project Assurance.

Key takeaway: Project Assurance is there to support the Project Board and to assure them that the project is being run correctly. To have the Project Manager assume this role as well would be a conflict of interests.