66. Which document contains the planned and actual dates for product approval and hand-over?
  1. Project Plan
  2. Stage Plan
  3. Product Checklist
  4. Project Brief
67. A successful project is which of the following?
  1. Output-oriented, not activity-oriented.
  2. Completed within the original timeframe.
  3. One which involves no change.
  4. Delivered under budget.
68. Which role confirms stage and project progress against agreed tolerances?
  1. Project Board
  2. Project Assurance
  3. Project Support
  4. Project Manager
69. Which of the following is NOT a PRINCE2 process?
  1. Directing a Project
  2. Assessing a Project
  3. Controlling a Stage
  4. Closing a Project
70. Which PRINCE2 theme addresses the ongoing viability of the different project plans?
  1. Quality
  2. Plans
  3. Change
  4. Progress