Which of the following attributes should the project board have?
  1. Experience of Quality control.
  2. Sufficient authority to allocate resources.
  3. Knowledge of PRINCE2.
  4. Knowledge of standards applicable to the project.
Explanation
Answer: B - Sufficient authority to allocate resources.

Key takeaway: Without sufficient authority to allocate the resources, be they business, supplier, or user, the Project Board cannot fulfil its basic function, and it will not be possible for the project to proceed.