Which of the following products is NOT related to the PRINCE2 approach to change?
  1. Configuration Management Strategy
  2. Quality Register
  3. Issue Register
  4. Daily Log
Explanation
Answer: B - Quality Register. This is, of course, related to the PRINCE2 approach to Quality.

Key takeaway: The PRINCE2 approach to Change includes a number of documents: Configuration Management Strategy, Configuration Item Records, Product Status Accounts, Daily Log, Issue Register, and Issue Reports.