Which role is responsible for defining the role descriptions within the project?
  1. Corporate or Programme Management
  2. Executive
  3. Project Manager
  4. Project Support
Explanation
Answer: C - Project Manager.

Key takeaway: The Executive and the Project Manager are the first two roles to be appointed. It is then the Project Manager's responsibility to define the other roles needed in the project (but not to assign people to those roles).