During which Process is the Work Package status reviewed?
  1. Directing a Project.
  2. Managing a Stage Boundary.
  3. Managing Product Delivery.
  4. Controlling a Stage.
Explanation
Answer: D - Controlling a Stage.

Key takeaway: The Team Manager will report back to the Project Manager, either in regular Checkpoint Reports, or to indicate that there is a new risk or issue.
Was this helpful? Upvote!
Login to contribute your own answer or details