You asked your friend Dixon, a program manager at PowerUp, to lunch. Dixon said he was swamped. He explained that he is using the coding structure to perform a certain process. Which process is Dixon most likely talking about?
  1. Human Resource Planning
  2. Decomposition
  3. Program Cost Estimating and Budgeting
  4. Program Schedule Development
Explanation
Answer - D - Dixon is talking about Program Schedule Development.

Key Takeaway: Program schedule development is the process of creating a schedule for the life of a given program. The schedule contains these steps: identifying components or activities, determining the dependencies among the components, estimating durations of the components, and finally, scheduling the components. A key tool used in this process is schedule network diagramming.