PgMP Program Management

Category - Domain 3

Which is NOT included in the input of the Communication Planning process?
  1. PWBS
  2. Communication management plan
  3. Program Charter
  4. Program scope statement
Explanation
Answer - B - The communication management plan is not an input to the Communication Planning process.

Key Takeaway: The Communication Planning process is: what information is needed, when, who needs it, and who will deliver it. To do this, it will be necessary to know the program scope and the proper requirements to plan communication, such as information for the proper stakeholders and technology requirements of the organization. Hence, inputs to the Communication Planning process are: program scope statement, PWBS, the program charter, the program reporting and communication requirements, and a stakeholder analysis chart.