The schedule management plan is an output of which of the following processes?
  1. Schedule Development
  2. Program Planning
  3. Schedule Planning
  4. Schedule Definition
Explanation
Answer - A - Schedule Development generates the schedule management plan.

Key Takeaway: The Schedule Development process generates two outputs: a program schedule and a schedule management plan. Remember that the creation of a program schedule is basically road mapping how you will ultimately execute the program. Schedule Development involves defining the program components (component definition), configuring the order in which the components will be executed (component sequencing), figuring out how much time it will take to complete each component (component duration estimating), and assigning an accurate timeline for completing the components (component scheduling).