Which is NOT an output of the Schedule Control process?
  1. Performance reports
  2. Change requests
  3. Updates to the program schedule
  4. Information for stakeholders
Explanation
Answer - A -Performance reports are not an output of the Schedule Control process.

Key Takeaway: The Schedule Control process ensures the program is completed within time according to the approved schedule. The output to the Schedule Control process include: information for stakeholders, updates to program schedule, and change requests. Performance reports are an input to the Schedule Control process.