The Black Forest Tie Affair program is currently in the planning stages. Its program sponsor, Randolph Moneypenny, says to Miguel, the program manager, “I need an organizational chart. Please perform this process.” Which process is Mr. Moneypenny speaking of?
  1. Human Resource Planning
  2. Resource Planning
  3. Organizational Planning
  4. Schedule Development
Explanation
Answer - A - Mr. Moneypenny is referring to the Human Resource Planning process.

Key Takeaway: The Human Resource Planning process is used to assign roles and responsibilities for given programs. It also generates a general staffing management plan. Anything involving staffing organization and acquisition falls under Human Resource Planning.