PgMP Program Management

Category - Domain 4

Which of the following are inputs to the Request Seller Responses process?
  1. Program preferred vendors list and evaluation criteria
  2. Program vendors list and request for quotations
  3. Evaluation criteria and request for information
  4. Request for quotations and request for information
Explanation
Answer - A - Program preferred vendors list and evaluation criteria are inputs to the Request Seller Responses process.

Key Takeaway: The Request Seller Responses process obtains responses in terms of quotations, offers, proposals, and bids from sellers outside the program team for their product or services needed for the program. The input to this process includes the program preferred vendor list and evaluation criteria. From this input responses can be sought through using various techniques.