PgMP Program Management

Category - Domain 5

Which is NOT an input to the Scope Control process?
  1. Program schedule
  2. Program scope
  3. Program budget
  4. Performance reports
Explanation
Answer - B - Program scope is not an input to the Scope Control process.

Key Takeaway: The Scope Control process controls any changes to the program scope. The input to the Scope Control process includes elements that define the scope: change requests, program budget, program schedule, program scope statement and scope management plan, program work breakdown structure, and performance reports.
Was this helpful? Upvote!