PgMP Program Management

Category - Domain 3

The Project Management Information System acts as a/an ____ to many program and project management processes.
  1. Tool and technique
  2. Output
  3. Input
  4. QA
Explanation
Answer - A - The Project Management Information System, or PMIS, acts as a tool and technique to many program and project management processes.

Key Takeaway: The Project Management Information System (PMIS) is an information system that gathers, combines, and stores various outputs of the project management processes. PMIS also controls changes to any of the important project documents. PMIS contains mostly automated tools and is used throughout the life cycle of a project, from initiation to closing.