PgMP Program Management

Category - Domain 5

Which of the following are Monitoring and Controlling processes which belong to the Integration Management knowledge area?
  1. Integrated Change Control, Monitor and Control Program Work, and Performance Reporting
  2. Resource Control, Issue Management and Control, and program Contract Administration
  3. Resource Control, Issue Management and Control, and Monitor and Control Program Work
  4. Resource Control, Issue Management and Control, and Communication Control
Explanation
Answer - C - Resource Control, Issue Management and Control, and Monitor and Control Program Work are Monitoring and Controlling processes that belong to the Integration Management knowledge area.

Key Takeaway: The Integration Management knowledge area is comprised of four planning processes: the Develop Program Management Plan, Interface Planning, Resource Planning, and Transition Planning. Integration Plans refer to the big picture aspect of planning a program that will require integrating several different departments/processes and coordinating those processes across several different groups and/or knowledge areas.