PgMP Program Management

Category - Domain 5

Which is NOT an output of the Monitor and Control Program Work process?
  1. Forecasts
  2. Change requests
  3. Performance reports
  4. Communication messages
Explanation
Answer - C - Performance reports are not an output of the Monitor and Control Program Work process.

Key Takeaway: All work completed in a program is monitored and controlled using the Monitor and Control Program Work process. The key outputs to the process are change requests, forecasts, and communication messages. Performance reports are an output to the Develop Program Team process.