What does it mean to tailor PRINCE2 to the project environment?

  1. Some elements of PRINCE2 should be omitted
  2. The principles should be adapted depending on the environment
  3. The methods should be adapted to suit the circumstances
  4. Blind obedience to project processes should be avoided
  1. 1 and 2
  2. 2 and 3
  3. 1 and 4
  4. 3 and 4
Explanation

Answer: D - The 'robotic' route of blind obedience should be avoided at all costs.

Key Takeaway: Without adherence to the principles of PRINCE2, a project cannot be classed as a PRINCE2 project. Whilst certain elements can be merged or dealt with very briefly, it is not advisable to simply omit anything.

Was this helpful? Upvote!
Login to contribute your own answer or details