What is the PRINCE2 term for a deliverable?

  1. Item
  2. Process
  3. Product
  4. Work Package
Explanation

Answer: C - Product. This is in line with the PRINCE2 principle of Focus on Products.

Key Takeaway: All deliverables within a PRINCE2 project are products. This includes not only the final product, but all documents and other items that may be created during the project. For example, the Lessons Log and Risk Management Strategy are both products and should be treated as such.

Was this helpful? Upvote!
Login to contribute your own answer or details