When a work package is returned, which of the following actions does PRINCE2 recommend?

  1. Notify the Project Board
  2. Update the Team Plan
  3. Review the Approval Records
  4. Update the Stage Plan
  1. 1 and 2
  2. 2 and 3
  3. 1, 2, and 3
  4. 1, 3, and 4
Explanation

Answer: B - A Work Package delivery involves the Team Manager and the Project Manager.

Key takeaway: The Project Manager has sole responsibility for dealing with the Team Manager and associated Work Packages. It is only if tolerances for the stage are exceeded that the Project Board needs to be involved.

Was this helpful? Upvote!
Login to contribute your own answer or details