In which of the following reports are risks communicated?

  1. Checkpoint Reports
  2. Highlight Reports
  3. Lessons Reports
  4. End Project Reports
  1. 1, 2
  2. 1, 3
  3. 1, 2, 3
  4. 1, 2, 3, 4
Explanation

Answer: D - Risks are communicated in all these reports, as well as the End Stage Report.

Key takeaway: It is important that Risks are communicated as soon as possible so that all stakeholders are aware and suitable action can be recommended and taken. The only exception is when informing external stakeholders about risks, which may require extra care. In this instance the Communication Management Strategy should provide the appropriate guidelines.

Was this helpful? Upvote!
Login to contribute your own answer or details