81. Is it possible for the members of the Project Board to provide guidance to the Project Manager outside the standard documentation/reporting procedures specified in PRINCE2?
  1. No. Communication from the Project Board must always occur at predefined points.
  2. Yes, but only in response to a PRINCE2 report from the Project Manager.
  3. Yes, but only if the Project Manager specifically requests guidance.
  4. Yes. They are allowed to give ad-hoc direction any time they like.
82. During which process is the request to approve the next Stage Plan made?
  1. Controlling a Stage
  2. Managing a Stage Boundary
  3. Directing a Project
  4. Closing a Project
83. Which role is responsible for drafting the outline Business Case?
  1. Executive
  2. Project Manager
  3. Corporate or Programme Management
  4. Senior Supplier
84.

The purpose of Configuration Management is:

  1. To create products
  2. To track products
  3. To define products
  4. To approve products
85.

According the Prince2 principles, the scope of a plan is defined by:

  1. The expected benefits
  2. The quality requirements
  3. The target completion dates
  4. The set of products to be delivered