Which process triggers the request to deliver a project?
  1. Starting up a Project
  2. Directing a Project
  3. Initiating a Project
  4. Managing Product Delivery
Explanation
Answer: C - Initiating a Project. At this point, only management products have been produced.

Key takeaway: The initiation stage assembles all the relevant project information in the form of the Project Initiation Document. This is then presented to the Project Board, who will then decide whether or not to proceed with the project.