86.

Which of the following do progress controls help with?

  1. Quality controls
  2. Authorization of further work
  3. Problem detection and risk identification
  4. Comparing the level of achievement with the plan
  1. 1, 4
  2. 3, 4
  3. 1, 2, 4
  4. 2, 3, 4
87. Which product is an input for the Closing a Project process?
  1. The Project Mandate
  2. The Project Initiation Documentation
  3. The previous Stage Plan
  4. The previous End Stage Report
88. What name is given to the piece of work performed by a Team Manager for the Project Manager?
  1. Work Package
  2. Team Plan
  3. Product Description
  4. Project Product Description
89.

Which of the following activities does PRINCE2 recommend when preparing the Communication Management Strategy?

  1. Review the project brief
  2. Review the risk and issue registers
  3. Consult with the suppliers that will be used throughout the project
  4. Consult with project assurance
  1. 1, 2
  2. 3, 4
  3. 1, 2, 4
  4. 2, 3, 4
90. Which 3 products are created once the authority to initiate the project has been received?
  1. Risk Management Strategy, Quality Management Strategy, Communication Management Strategy
  2. Project Plan, Configuration Management Strategy, Quality Management Strategy
  3. Project Plan, Risk Management Strategy, Quality Management Strategy
  4. Risk Management Strategy, Quality Management Strategy, Configuration Management Strategy