According the Prince2 principles, the scope of a plan is defined by:

  1. The expected benefits
  2. The quality requirements
  3. The target completion dates
  4. The set of products to be delivered
Explanation

Answer: D - According the Prince2 principles, the scope of a plan is defined by the set of products to be delivered.

Key takeaway: One of the principles of a PRINCE2 project is Focus on Products. It is the products which define a project (as opposed to the activities or processes). As such, the scope of the project is also defined by the products to be delivered.

Was this helpful? Upvote!