Which of the true is following about projects?

  1. They are driven by deliverables
  2. They have finite timescales
  3. They involve changes to the business capability
  4. They have benefits that are usually realized after project closure
  1. 1, 2
  2. 1, 2, 3
  3. 2, 3, 4
  4. 1, 2, 4
Explanation

Answer: D - A project has a finite timespan, is driven by its products, and has benefits that are usually seen once the project is complete.

Key takeaway: It is important to understand the difference between a Project and a Programme. A Programme is more open ended; it has no pre-defined path, runs on a longer timescale than projects, and can affect the business capability. It is driven by a business vision of how things should be at an undefined date in the future. Projects within the Programme will all contribute to this vision in some way.