1. Which of the following is a principle of PRINCE2?
  1. Manage change
  2. Manage by stages
  3. Manage by tolerance
  4. Manage risk
2.

Which of the following two roles sit on the project board?

  1. Project manager
  2. Executive
  3. Senior user
  4. Project assurance
  1. 1, 2
  2. 2, 3
  3. 1, 4
  4. 3, 4
3. Which of the following documents is NOT produced within a PRINCE2 project?
  1. Lessons log
  2. Project mandate
  3. Project manager role description
  4. Stage plan
4. James Kirk is the project manager for a 5-year project, with a time tolerance of +3 months for the current stage. One of his team leaders, Monty Scott, reports a projected problem with a work package that is expected to take an extra 2 weeks. What action should Kirk take?
  1. None
  2. Produce an Exception Report.
  3. Cancel the project.
  4. Add an entry to the Risk Register.
5. Which document defines the acceptance criteria and roles for the project?
  1. Project Initiation Document
  2. Project Mandate
  3. Project Product Description
  4. Quality Management Strategy