Which document defines the acceptance criteria and roles for the project?
  1. Project Initiation Document
  2. Project Mandate
  3. Project Product Description
  4. Quality Management Strategy
Explanation
Answer: C - Project Product Description. This is created in the Starting up a Project process and used during the Closing a Project process to help verify that the project has delivered to expectations.

Key takeaway: The project product description is a special case of the more general product description. It defines what the project must deliver as a whole in order to be accepted.